Hi,

I'm a bit confused about how electricity process is modeled in ecoinvent.

For example, if I want to change the default electricity mix, which dataset should I edit? :

Electricity, high voltage {MY}| market for | APOS, U

or

Electricity, high voltage {MY}| production mix | APOS, U

The electricity that I will be using is the medium voltage (Electricity, medium voltage {MY}| market for | APOS, U). However, it's related to both of the above. Also, I noticed that PV is included at the low voltage dataset. How do I include PV resource in the electricity mix?

Thanks.