I'm trying to implement a connected process.

First, there is a process that I made.

Second, I made the process by putting the first I made process into the input data.

But in the model graph of the second process, the input data is not connected.

In the model graph, only output data appears.

What's wrong? I'd appreciate it if you could tell me the solution.
in openLCA by (190 points)

1 Answer

0 votes
by (125k points)
Hm, you do not put a process into the input data - do you mean, the product (of the process)? Ideally post a picture, that would be easier to understand.