0 votes
433 views
Hi! I am trying to create a new process in PSILCA and I am finding hard to calculate the working hours. I know that the equation is

worker hours=unit labour cost/mean hourly labour cost

But to calculate in a new process the working hours should I use the data from Eora and ILOSTAT(to find the unit labour cost and the hourly labour cost)?

Thank you :)
in openLCA by (330 points)

1 Answer

0 votes
by (126k points)
Ideally, you use data from your own process, i.e. from the process you are modeling, as a backup, you can use those from the database (PSILCA) for the same sector and country.
by (150 points)
just out of clarity, this all means that we cannot find the (calculated) worker hours values in the PSILCA database, nor are they computed in results? I cannot find them back, only converted ones in risk hours. Yet, I wondered whether I just couldn't find them or they are not there.
...