Just take a random ecoinvent process and do the same test. I'm sorry but I can't help for your own processes, where I don't know the details and where you first wrote that you checked and the provider are correct and then later wrote that there was a different link in the provider.
You can also see in the contribution tree where the difference is coming from. You can see there if the difference is from a flow, from an amount value, from a characterization factor, from a different provider etc.
If nothing works and if the issue is not only with your own processes (that I don't know), you can send a mail with more details on the process. But because you said that "It's the only value out of control (C4: Manutenzione infrastruttura) all the other are ok now.", it is most likely an issue that is related to your own process that you created.