Hello everyone,
as part of my master thesis, I have to carry out a life-cycle assessment with the ecoinvent database (version 3.6). This is about demolition, transport and sorting processes of reinforced concrete. I have already understood that one connects processes in which the output (quantitative reference) of process 1 must correspond to the input of the subsequent process 2.
1) Does this also apply to existing processes of the ecoinvent database? Can I then simply create a new flow and replace this flow as output (process 1) and insert this flow as input (process 2) into the respective database process and set the quantitative reference at process 1 (output) to my created flow? Or is data lost?
An example (green = quantitative reference with [unit] of the existing process):
- Process 1: excavation, hydraulic digger (ecoinvent: demolition process with excavator): Input: diesel, oil, digger.., Output: waste mineral oil,..., excavation, hydraulic digger [m3]
- Process 2: transport, freight, lorry >32 metric ton (ecoinvent: transport from concrete demolition to sorting plant): Input: diesel, road.., Output: road wear emission,.., transport freight, lorry >32 metric ton [t*km]
- Process 3: machine operation, diesel, >= 74.57 kW, steady-state (ecoinvent: processing/sorting of log material): Input: diesel, oil, Building machine.., Output: waste mineral oil, ..., machine operation diesel [h]
I want to link these 3 processes. The material of the demolition (crushed concrete) does not change from process 1, to process 2 to process 3.
Can I now do the following:
Creation of new product flows (for linking the processes):
- reinforced waste concrete = New quantitative reference = Input in following process
- recycled aggregate = New quantitative reference
And then:
- Process 1: excavation, hydraulic digger (ecoinvent: demolition process with excavator): Input: diesel, oil, digger.., Output: waste mineral oil,..., excavation, hydraulic digger, waste reinforced concrete [m3]
- Process 2: transport, freight, lorry >32 metric ton (ecoinvent: transport from concrete demolition to sorting plant): Input: waste reinforced concrete, diesel, road.., Output: road wear emission,.., transport freight, lorry >32 metric ton, waste reinforced concrete [t*km]
- Process 3: machine operation, diesel, >= 74.57 kW, steady-state (ecoinvent: processing/sorting of log material): Input: waste reinforced concrete, diesel, oil, building machine.., output: waste mineral oil, ..., machine operation diesel, recycled aggregate [m3]
2) Do you need to create new product flows or use existing product flows from the database to link the processes?
3) And do I have to copy the individual processes into a separate folder before I edit them, link them together and merge them into a product system?
I know that the questions are very extensive - but the subject is also very complicated.